Tuesday, October 29, 2013

At work again.

The same workman were back so I drove down to take a look.
(sorry, no picture. Didn't have camera with me)
Their trucks all said "Harvest Monovia Water Authority".
They were in a ditch down in the creek bed. I surmise that they are moving/replacing/repairing a water main that was cut to install the new bridge foundation (seen in this earlier picture - the green pipe below the raccoon).
I hate to think that the half month delay we just went through was waiting for the County to come and do this.





(I believe this is the pipe the county was working on. This photo was taken on the 10/31)

Monday, October 28, 2013

Finally back to work!

Sorry, no time for a photo today but I did see work crews on site this afternoon.
Let's hope this is a trend that continues.

Saturday, October 19, 2013

Take the week off.


One of these photos is from last Tuesday ... one is from Friday.

 

 

 

 

If there doesn't seem to be  any difference it's because nothing was done on the site this week.

 

Thursday, October 17, 2013

Wednesday, October 16, 2013

No work today.

No sign of workers.  

Drizzling rain today for a total of .46 inches. (rain gauge within a mile of the site)

Tuesday, October 15, 2013

What's Next?

 The site sat quite today, with no sign of workers.
So, with the completion (?) of the foundations 
and the removal of the excavators, we wait.
What's next?

Monday, October 14, 2013

Foundation work is done???



Apparently the Foundation work is complete. The last excavator is loaded up for removal.

 Two things of interest. Notice the new concrete foundation now underwater and the large earthen berm in the background. That newly worked (and apparently seeded and hayed) dam sits on a subdivision lot that had remained un-built on. I assume no one ever chose to build there because it was flood prone and would have been to expensive for an individual to raise to a safe level. Has the County has now purchased that lot and paid to put the dam there?

Ready for a bridge.

Friday, October 11, 2013

Tuesday, October 8, 2013

Saturday, October 5, 2013

Pile Driving is Finished?

The crane remains but the pile driver seems to have been removed.


The ditches with the pilings have all been allowed to flood now.



Seems the workers find our creek a better place to throw their trash.